PK0-005 · Question #609
A project team member recalls a specific discussion with another team member. The discussion addressed key information that was not documented and was related to a previous project. Which of the…
The correct answer is D. Lessons learned. Lessons learned capture important insights, decisions, and knowledge from projects so they are formally documented and available for future projects, preventing reliance on individual memory for critical information.
Question
A project team member recalls a specific discussion with another team member. The discussion addressed key information that was not documented and was related to a previous project. Which of the following steps should help avoid this scenario in the future?
Options
- AIntegrity
- BSecurity
- CArchival
- DLessons learned
How the community answered
(47 responses)- A11% (5)
- B6% (3)
- C2% (1)
- D81% (38)
Explanation
Lessons learned capture important insights, decisions, and knowledge from projects so they are formally documented and available for future projects, preventing reliance on individual memory for critical information.