PK0-005 · Question #607
Which of the following activities is performed during the project closure phase when the waterfall methodology is being used? (Choose two.)
The correct answer is E. Validating the deliverables F. Reconciling the project budget. During the project closure phase in a waterfall methodology, deliverables are formally validated to confirm they meet acceptance criteria and can be handed over. The project budget is also reconciled to ensure all costs are accounted for and financial closure is completed.
Question
Which of the following activities is performed during the project closure phase when the waterfall methodology is being used? (Choose two.)
Options
- ACreating a backlog
- BManaging the quality of deliverables
- CUpdating the issue log
- DPerforming a risk assessment
- EValidating the deliverables
- FReconciling the project budget
How the community answered
(64 responses)- B2% (1)
- D3% (2)
- E95% (61)
Explanation
During the project closure phase in a waterfall methodology, deliverables are formally validated to confirm they meet acceptance criteria and can be handed over. The project budget is also reconciled to ensure all costs are accounted for and financial closure is completed.