nerdexam
CompTIA

PK0-005 · Question #597

Which of the following tasks should the PM complete first when validating deliverables?

The correct answer is C. Review the project objectives. When validating deliverables, the first task is to compare them against the documented project objectives to ensure they meet the intended requirements. This provides the basis for determining whether stakeholder feedback or further assessment is needed.

Project Management Concepts

Question

Which of the following tasks should the PM complete first when validating deliverables?

Options

  • AAssess the documentation.
  • BObtain stakeholder feedback.
  • CReview the project objectives.
  • DMitigate risks.

How the community answered

(29 responses)
  • A
    10% (3)
  • B
    3% (1)
  • C
    83% (24)
  • D
    3% (1)

Explanation

When validating deliverables, the first task is to compare them against the documented project objectives to ensure they meet the intended requirements. This provides the basis for determining whether stakeholder feedback or further assessment is needed.

Topics

#Deliverable validation#Project objectives#Quality control#Project management process

Community Discussion

No community discussion yet for this question.

Full PK0-005 Practice