PK0-005 · Question #595
A project manager is assigned to a project that has contracted with vendors. Which of the following actions should the project manager most frequently take? (Choose two.)
The correct answer is D. Monitor performance. E. Approve deliverables.. When managing vendor contracts, the project manager must frequently monitor vendor performance to ensure contract compliance and project alignment. Additionally, the PM must approve deliverables from vendors to confirm they meet agreed-upon requirements before
Question
A project manager is assigned to a project that has contracted with vendors. Which of the following actions should the project manager most frequently take? (Choose two.)
Options
- AUpdate the issue log.
- BCreate a project charter.
- CValidate the status report.
- DMonitor performance.
- EApprove deliverables.
- FBaseline the project schedule.
How the community answered
(54 responses)- A4% (2)
- B11% (6)
- C6% (3)
- D78% (42)
- F2% (1)
Explanation
When managing vendor contracts, the project manager must frequently monitor vendor performance to ensure contract compliance and project alignment. Additionally, the PM must approve deliverables from vendors to confirm they meet agreed-upon requirements before