The correct answer is B: Send a request to the functional manager to increase project allocation that prioritizes the. Since the developer is already committed to multiple tasks, the project manager should work with the functional manager to adjust resource allocation. This ensures the developer’s workload is prioritized properly for the critical project task.

Project Management Concepts

Question

A project manager is consistently struggling to obtain a commitment date from a developer to deliver a major task. The developer tells the project manager that multiple tasks are already planned. Which of the following actions should the project manager take?

Options

  • AEscalate to human resources to terminate the developer due to lack of project interest.
  • BSend a request to the functional manager to increase project allocation that prioritizes the
  • CNotify the developer that a specific deliverable date has been updated on the schedule.
  • DAssign a new developer to be in charge of the critical task.

Explanation

Since the developer is already committed to multiple tasks, the project manager should work with the functional manager to adjust resource allocation. This ensures the developer’s workload is prioritized properly for the critical project task.

Topics

#Resource Management#Stakeholder Communication#Task Prioritization#Conflict Resolution