A project team is deciding how to break up a large project into smaller components so the project can be delivered without increasing the duration of the iteration cycles. Which of the following…

The correct answer is D. An epic. In agile, a large body of work is grouped as an epic. Epics are then broken down into smaller backlog items (such as user stories) so they can be delivered incrementally within shorter iteration cycles.

Project Management Concepts

Question

A project team is deciding how to break up a large project into smaller components so the project can be delivered without increasing the duration of the iteration cycles. Which of the following describes the grouping of the smaller components?

Options

  • AAn issue
  • BA goal
  • CA backlog item
  • DAn epic

How the community answered

(57 responses)
  • B
    2% (1)
  • C
    4% (2)
  • D
    95% (54)

Explanation

In agile, a large body of work is grouped as an epic. Epics are then broken down into smaller backlog items (such as user stories) so they can be delivered incrementally within shorter iteration cycles.

Topics

#Agile methodologies#Project decomposition#Epics#Work breakdown structure