nerdexam
CompTIACompTIA

PK0-005 · Question #586

PK0-005 Question #586: Real Exam Question with Answer & Explanation

The correct answer is A: Conduct impact assessment.. After documenting a change request, the next step is to conduct an impact assessment to evaluate how the change will affect project scope, schedule, cost, and quality before it is reviewed by the Change Control Board (CCB).

Project Management Concepts

Question

As a result of an unpredicted issue during a demo presentation, a project manager is documenting a change request to the CCB. Which of the following should the project manager do next?

Options

  • AConduct impact assessment.
  • BValidate the implementation.
  • CCommunicate to stakeholders.
  • DDocument the recommendations.

Explanation

After documenting a change request, the next step is to conduct an impact assessment to evaluate how the change will affect project scope, schedule, cost, and quality before it is reviewed by the Change Control Board (CCB).

Topics

#Change Management#Change Request#Impact Assessment#Project Processes

Community Discussion

No community discussion yet for this question.

Full PK0-005 PracticeBrowse All PK0-005 Questions