PK0-005 · Question #586
PK0-005 Question #586: Real Exam Question with Answer & Explanation
The correct answer is A: Conduct impact assessment.. After documenting a change request, the next step is to conduct an impact assessment to evaluate how the change will affect project scope, schedule, cost, and quality before it is reviewed by the Change Control Board (CCB).
Question
As a result of an unpredicted issue during a demo presentation, a project manager is documenting a change request to the CCB. Which of the following should the project manager do next?
Options
- AConduct impact assessment.
- BValidate the implementation.
- CCommunicate to stakeholders.
- DDocument the recommendations.
Explanation
After documenting a change request, the next step is to conduct an impact assessment to evaluate how the change will affect project scope, schedule, cost, and quality before it is reviewed by the Change Control Board (CCB).
Topics
Community Discussion
No community discussion yet for this question.