PK0-005 · Question #584

PK0-005 Question #584: Real Exam Question with Answer & Explanation

The correct answer is D: Add risk into the risk register.. Since the regulatory changes have not yet occurred but are expected, they represent a potential risk to the project. The project manager should document this in the risk register so it can be monitored and addressed through risk response planning.

Project Management Concepts

Question

A project sponsor tells the project manager that new regulatory environment changes are coming in the next month. Which of the following should the project manager do next?

Options

  • ARegister the issue in the issue log.
  • BProvide the change to the CCB.
  • CImplement a work-around.
  • DAdd risk into the risk register.

Explanation

Since the regulatory changes have not yet occurred but are expected, they represent a potential risk to the project. The project manager should document this in the risk register so it can be monitored and addressed through risk response planning.

Topics

#Risk Management#Risk Identification#Project Planning#Regulatory Impact