A project sponsor tells the project manager that new regulatory environment changes are coming in the next month. Which of the following should the project manager do next?

The correct answer is D. Add risk into the risk register. Since the regulatory changes have not yet occurred but are expected, they represent a potential risk to the project. The project manager should document this in the risk register so it can be monitored and addressed through risk response planning.

Project Management Concepts

Question

A project sponsor tells the project manager that new regulatory environment changes are coming in the next month. Which of the following should the project manager do next?

Options

  • ARegister the issue in the issue log.
  • BProvide the change to the CCB.
  • CImplement a work-around.
  • DAdd risk into the risk register.

How the community answered

(14 responses)
  • A
    7% (1)
  • B
    14% (2)
  • D
    79% (11)

Explanation

Since the regulatory changes have not yet occurred but are expected, they represent a potential risk to the project. The project manager should document this in the risk register so it can be monitored and addressed through risk response planning.

Topics

#Risk Management#Risk Identification#Project Planning#Regulatory Impact