PK0-005 · Question #584
PK0-005 Question #584: Real Exam Question with Answer & Explanation
The correct answer is D: Add risk into the risk register.. Since the regulatory changes have not yet occurred but are expected, they represent a potential risk to the project. The project manager should document this in the risk register so it can be monitored and addressed through risk response planning.
Question
A project sponsor tells the project manager that new regulatory environment changes are coming in the next month. Which of the following should the project manager do next?
Options
- ARegister the issue in the issue log.
- BProvide the change to the CCB.
- CImplement a work-around.
- DAdd risk into the risk register.
Explanation
Since the regulatory changes have not yet occurred but are expected, they represent a potential risk to the project. The project manager should document this in the risk register so it can be monitored and addressed through risk response planning.
Topics
Community Discussion