The correct answer is D: PERT chart. A PERT (Program Evaluation and Review Technique) chart is best for planning because it helps calculate task durations, map dependencies, and analyze the critical path, making it ideal for defining the full scope and schedule in the planning phase.
Question
During the planning phase, a project manager is mapping out the full scope, calculating task durations, and identifying dependencies. Which of the following is the best tool for the project manager to use?
Options
- AGantt chart
- BMilestone chart
- CVelocity chart
- DPERT chart
Explanation
A PERT (Program Evaluation and Review Technique) chart is best for planning because it helps calculate task durations, map dependencies, and analyze the critical path, making it ideal for defining the full scope and schedule in the planning phase.