PK0-005 · Question #577
During the lessons learned session, an agile project team identified that a WBS could have helped clarify the scope. Which of the following best describes the benefits of having a WBS completed…
The correct answer is B. Facilitates the process of developing a schedule. A Work Breakdown Structure (WBS) breaks down the project scope into manageable tasks, making it easier to estimate durations and resources. This directly supports the development of a realistic and organized project schedule.
Question
During the lessons learned session, an agile project team identified that a WBS could have helped clarify the scope. Which of the following best describes the benefits of having a WBS completed during planning stages?
Options
- ADetermines the processes to be used during quality assurance
- BFacilitates the process of developing a schedule
- CIdentifies the ground rules for operational handoff
- DEstablishes the governance of a project
How the community answered
(23 responses)- A4% (1)
- B91% (21)
- D4% (1)
Explanation
A Work Breakdown Structure (WBS) breaks down the project scope into manageable tasks, making it easier to estimate durations and resources. This directly supports the development of a realistic and organized project schedule.
Topics
Community Discussion
No community discussion yet for this question.