The project team is preparing to upgrade the organization's servers to comply with company standards. Which of the following should the team do first?
The correct answer is C. Assess the compatibility. The team should first assess the compatibility of the new servers with existing systems to ensure the upgrade can proceed smoothly and without unforeseen technical issues.
Project Management Concepts
Question
The project team is preparing to upgrade the organization's servers to comply with company standards. Which of the following should the team do first?
Options
- ADevelop an SOW.
- BPrepare an issue log.
- CAssess the compatibility.
- DCreate a rollback plan.
How the community answered
(42 responses)- A2% (1)
- B7% (3)
- C71% (30)
- D19% (8)
Explanation
The team should first assess the compatibility of the new servers with existing systems to ensure the upgrade can proceed smoothly and without unforeseen technical issues.