CompTIA
PK0-005 · Question #541
As a result of an internal audit, a project manager executes an approved change from the CCB. Which of the following change control process actions should the project manager complete next?
The correct answer is D. Validate the change was successfully implemented. After executing an approved change, the project manager should validate that the change was successfully implemented to ensure it achieved the intended results and meets project
Project Management Concepts
Question
As a result of an internal audit, a project manager executes an approved change from the CCB. Which of the following change control process actions should the project manager complete next?
Options
- ARequest the auditor to submit a change request.
- BDocument internal audit findings in the change control log.
- CAsk the project team to evaluate the change.
- DValidate the change was successfully implemented.
How the community answered
(31 responses)- A3% (1)
- B10% (3)
- C6% (2)
- D81% (25)
Explanation
After executing an approved change, the project manager should validate that the change was successfully implemented to ensure it achieved the intended results and meets project
Topics
#Change Management#Change Control Process#Project Audit#Validation
Community Discussion
No community discussion yet for this question.