nerdexam
CompTIACompTIA

PK0-005 · Question #541

PK0-005 Question #541: Real Exam Question with Answer & Explanation

Sign in or unlock PK0-005 to reveal the answer and full explanation for question #541. The question stem and answer options stay visible for context.

Project Management Concepts

Question

As a result of an internal audit, a project manager executes an approved change from the CCB. Which of the following change control process actions should the project manager complete next?

Options

  • ARequest the auditor to submit a change request.
  • BDocument internal audit findings in the change control log.
  • CAsk the project team to evaluate the change.
  • DValidate the change was successfully implemented.

Unlock PK0-005 to see the answer

You've previewed enough free PK0-005 questions. Unlock PK0-005 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Change Management#Change Control Process#Project Audit#Validation
Full PK0-005 PracticeBrowse All PK0-005 Questions