PK0-005 · Question #541

As a result of an internal audit, a project manager executes an approved change from the CCB. Which of the following change control process actions should the project manager complete next?

The correct answer is D. Validate the change was successfully implemented. After executing an approved change, the project manager should validate that the change was successfully implemented to ensure it achieved the intended results and meets project

Project Management Concepts

Question

As a result of an internal audit, a project manager executes an approved change from the CCB. Which of the following change control process actions should the project manager complete next?

Options

  • ARequest the auditor to submit a change request.
  • BDocument internal audit findings in the change control log.
  • CAsk the project team to evaluate the change.
  • DValidate the change was successfully implemented.

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    10% (3)
  • C
    6% (2)
  • D
    81% (25)

Explanation

After executing an approved change, the project manager should validate that the change was successfully implemented to ensure it achieved the intended results and meets project

Topics

#Change Management#Change Control Process#Project Audit#Validation