Which of the following would help the project manager to create a SOW for the vendor? (Choose two.)

The correct answer is A. Expected outcomes C. Schedule period. Expected outcomes define the deliverables and results required from the vendor, which are essential for the SOW. Schedule period specifies the timeframe for deliverables, helping to set clear expectations in the

Project Management Concepts

Question

Which of the following would help the project manager to create a SOW for the vendor? (Choose two.)

Options

  • AExpected outcomes
  • BOperational expenses
  • CSchedule period
  • DRisk analysis
  • EIssue description
  • FStatus report

How the community answered

(56 responses)
  • A
    95% (53)
  • D
    2% (1)
  • E
    4% (2)

Explanation

Expected outcomes define the deliverables and results required from the vendor, which are essential for the SOW. Schedule period specifies the timeframe for deliverables, helping to set clear expectations in the

Topics