A project manager is facilitating a meeting where the attendees cannot reach agreement on a decision. Which of the following actions should the project manager take?

The correct answer is A. The project manager must discuss the decision with stakeholders to reach a consensus. When the team cannot reach agreement, the project manager should engage stakeholders to reach a consensus, ensuring that the decision aligns with project goals and has support from key

Project Management Concepts

Question

A project manager is facilitating a meeting where the attendees cannot reach agreement on a decision. Which of the following actions should the project manager take?

Options

  • AThe project manager must discuss the decision with stakeholders to reach a consensus.
  • BThe decision must be made based only on one stakeholder's needs.
  • CTeam members must make a decision without the project manager's permission.
  • DThe project manager must independently make the decision.

How the community answered

(37 responses)
  • A
    81% (30)
  • B
    11% (4)
  • C
    5% (2)
  • D
    3% (1)

Explanation

When the team cannot reach agreement, the project manager should engage stakeholders to reach a consensus, ensuring that the decision aligns with project goals and has support from key