nerdexam
CompTIACompTIA

PK0-005 · Question #518

PK0-005 Question #518: Real Exam Question with Answer & Explanation

The correct answer is C: The project sponsor is expecting to have a minimum viable product at the earliest release.. Choosing an agile framework is most appropriate when the project sponsor wants a minimum viable product (MVP) delivered early, as Agile supports incremental development and rapid delivery of functional components for early feedback and value realization.

Project Management Concepts

Question

Which of the following is the most likely reason for a project manager to choose an agile framework for a project?

Options

  • AThe project sponsor wants to have the entire product ready in a single deliverable.
  • BThe project sponsor wants to reduce the total cost of the project.
  • CThe project sponsor is expecting to have a minimum viable product at the earliest release.
  • DThe project sponsor did not get the CCB approval for a waterfall project.

Explanation

Choosing an agile framework is most appropriate when the project sponsor wants a minimum viable product (MVP) delivered early, as Agile supports incremental development and rapid delivery of functional components for early feedback and value realization.

Topics

#Agile methodologies#Project framework#MVP#Iterative development

Community Discussion

No community discussion yet for this question.

Full PK0-005 PracticeBrowse All PK0-005 Questions