PK0-005 · Question #516
PK0-005 Question #516: Real Exam Question with Answer & Explanation
The correct answer is A: It formalizes the completion of a project by obtaining stakeholder acceptance.. The key objective of a project sign-off is to formally acknowledge the completion of the project by obtaining stakeholder acceptance of the final deliverables, confirming that all requirements have
Project Life Cycle Phases
Question
Which of the following statements best represents the key objective of a project sign-off?
Options
- AIt formalizes the completion of a project by obtaining stakeholder acceptance.
- BIt celebrates project completion and triggers documentation archival.
- CIt approves the final budget review for a project and releases resources.
- DIt obtains business feedback on the project's product and formalizes contract closures.
Explanation
The key objective of a project sign-off is to formally acknowledge the completion of the project by obtaining stakeholder acceptance of the final deliverables, confirming that all requirements have
Topics
#Project sign-off#Project closure#Stakeholder acceptance#Deliverable acceptance