PK0-005 · Question #510

A project manager wants to review the deliverables outsourced in a project. Which of the following should the project manager use? (Choose two.)

The correct answer is B. SOW F. WBS. The Statement of Work (SOW) defines the scope, deliverables, and expectations for outsourced The Work Breakdown Structure (WBS) breaks down all project deliverables, including outsourced components, making it useful for review.

Tools and documentation

Question

A project manager wants to review the deliverables outsourced in a project. Which of the following should the project manager use? (Choose two.)

Options

  • ATOR
  • BSOW
  • CMOU
  • DRFP
  • ENDA
  • FWBS

How the community answered

(38 responses)
  • A
    11% (4)
  • B
    82% (31)
  • C
    5% (2)
  • D
    3% (1)

Explanation

The Statement of Work (SOW) defines the scope, deliverables, and expectations for outsourced The Work Breakdown Structure (WBS) breaks down all project deliverables, including outsourced components, making it useful for review.

Topics

#Outsourcing#Project Deliverables#Project Documentation#Scope Management