A project manager wants to review the deliverables outsourced in a project. Which of the following should the project manager use? (Choose two.)
The correct answer is B. SOW F. WBS. The Statement of Work (SOW) defines the scope, deliverables, and expectations for outsourced The Work Breakdown Structure (WBS) breaks down all project deliverables, including outsourced components, making it useful for review.
Tools and documentation
Question
A project manager wants to review the deliverables outsourced in a project. Which of the following should the project manager use? (Choose two.)
Options
- ATOR
- BSOW
- CMOU
- DRFP
- ENDA
- FWBS
How the community answered
(38 responses)- A11% (4)
- B82% (31)
- C5% (2)
- D3% (1)
Explanation
The Statement of Work (SOW) defines the scope, deliverables, and expectations for outsourced The Work Breakdown Structure (WBS) breaks down all project deliverables, including outsourced components, making it useful for review.
Topics
#Outsourcing#Project Deliverables#Project Documentation#Scope Management