PK0-005 · Question #478
PK0-005 Question #478: Real Exam Question with Answer & Explanation
The correct answer is C: The team is unclear which meetings they should attend. If team members are confused about which meetings to attend, this indicates a flaw in the communication plan. Revising the plan ensures clear expectations on who participates in which communication events. Scope or schedule changes don't automatically require altering the communi
Question
Which of the following situations would require a project manager to revise the communication plan during a project's execution?
Options
- AA change is approved that impacts the project schedule and budget
- BThe test results are not as expected
- CThe team is unclear which meetings they should attend
- DA stakeholder requests some changes to the scope
Explanation
If team members are confused about which meetings to attend, this indicates a flaw in the communication plan. Revising the plan ensures clear expectations on who participates in which communication events. Scope or schedule changes don't automatically require altering the communication plan.