The correct answer is C: The team is unclear which meetings they should attend. If team members are confused about which meetings to attend, this indicates a flaw in the communication plan. Revising the plan ensures clear expectations on who participates in which communication events. Scope or schedule changes don't automatically require altering the communi

Project Management Concepts

Question

Which of the following situations would require a project manager to revise the communication plan during a project's execution?

Options

  • AA change is approved that impacts the project schedule and budget
  • BThe test results are not as expected
  • CThe team is unclear which meetings they should attend
  • DA stakeholder requests some changes to the scope

Explanation

If team members are confused about which meetings to attend, this indicates a flaw in the communication plan. Revising the plan ensures clear expectations on who participates in which communication events. Scope or schedule changes don't automatically require altering the communication plan.

Topics

#Communication Plan#Stakeholder Communication#Project Execution#Project Management

Community Discussion

No community discussion yet for this question.

Full PK0-005 PracticeBrowse All PK0-005 Questions