A project manager must determine how ideas from the organization and results from the review committee should move through the enterprise for a new project. Which of the following does the project…
The correct answer is A. Establish communication channels. The correct step is to establish communication channels that ensure proper flow of information from idea origination through review and approval. Kickoff meetings occur later, while RACI matrices and stakeholder identification are planning tools -- not communication flow…
Question
A project manager must determine how ideas from the organization and results from the review committee should move through the enterprise for a new project. Which of the following does the project manager need to do?
Options
- AEstablish communication channels
- BPlan a kickoff meeting
- CDevelop a responsibility assignment matrix
- DIdentify the stakeholders
How the community answered
(43 responses)- A77% (33)
- B14% (6)
- C2% (1)
- D7% (3)
Explanation
The correct step is to establish communication channels that ensure proper flow of information from idea origination through review and approval. Kickoff meetings occur later, while RACI matrices and stakeholder identification are planning tools -- not communication flow structures.