nerdexam
CompTIA

PK0-005 · Question #463

Which of the following is part of software change control?

The correct answer is A. Rollback plans. A key element of change control is having a rollback plan, which allows recovery to a previous stable state if the change causes instability. This is part of operational support to maintain service availability and minimize downtime during updates.

Project Management Concepts

Question

Which of the following is part of software change control?

Options

  • ARollback plans
  • BMaintenance windows
  • CValidation checks
  • DRequirements definition

How the community answered

(32 responses)
  • A
    91% (29)
  • B
    6% (2)
  • C
    3% (1)

Explanation

A key element of change control is having a rollback plan, which allows recovery to a previous stable state if the change causes instability. This is part of operational support to maintain service availability and minimize downtime during updates.

Topics

#Change control#Rollback plans#Software management#IT operations

Community Discussion

No community discussion yet for this question.

Full PK0-005 Practice