Question
A project manager and team are reviewing a task that is supposed to take 9 days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in network that would add an additional 5 days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?
Options
- A9 days and $3,000
- B10 days and $3,200
- C12 days and $3,800
- D13 days and $3,600