While a team was in a work session developing the QA plan for a project, the project manager realized that the team lacks the skills required for proper quality assurance. Which of the following steps

The correct answer is A. Reassess the resource pool.. If the current team lacks the necessary skills for quality assurance, the project manager should reassess the resource pool to identify whether existing team members can be trained or if additional resources with the required expertise are needed. This assessment helps in making

Project Management Concepts

Question

While a team was in a work session developing the QA plan for a project, the project manager realized that the team lacks the skills required for proper quality assurance. Which of the following steps should the project manager take next?

Options

  • AReassess the resource pool.
  • BReview the QA plan from a similar project.
  • CCheck on available resources for additional team members.
  • DEscalate the issue to the project sponsor.

How the community answered

(50 responses)
  • A
    72% (36)
  • B
    4% (2)
  • C
    6% (3)
  • D
    18% (9)

Explanation

If the current team lacks the necessary skills for quality assurance, the project manager should reassess the resource pool to identify whether existing team members can be trained or if additional resources with the required expertise are needed. This assessment helps in making informed decisions about resource allocation, training needs, or recruitment, ensuring that the project maintains its quality standards.