PK0-005 · Question #440

Which of the following best describes the reason a waterfall approach would be used for a project?

The correct answer is B. The executive team is looking to review the product only once after the product is finalized. Waterfall is a sequential, phase-based methodology where each stage (requirements, design, development, testing, deployment) is completed before the next begins. The final product is delivered at the end of the process, making it ideal when stakeholders want a single review of…

Project Management Concepts

Question

Which of the following best describes the reason a waterfall approach would be used for a project?

Options

  • AThe executive team still has no clear requirements for the product.
  • BThe executive team is looking to review the product only once after the product is finalized.
  • CThe executive team is expecting constant delivery of components.
  • DThe executive team wants to reduce the budget for development.

How the community answered

(29 responses)
  • A
    3% (1)
  • B
    93% (27)
  • D
    3% (1)

Explanation

Waterfall is a sequential, phase-based methodology where each stage (requirements, design, development, testing, deployment) is completed before the next begins. The final product is delivered at the end of the process, making it ideal when stakeholders want a single review of the completed product rather than iterative feedback. If requirements are unclear (A), agile is preferred. Constant delivery of components (C) describes agile/continuous delivery. Reducing budget (D) is not a methodology-selection driver.

Topics

#Waterfall Model#Project Methodologies#Project Delivery#Stakeholder Engagement