PK0-005 · Question #438
During project initiation, a project manager is drafting a document that includes an outline of the high-level goals, objectives, milestones, and requirements. This document will be modified and…
The correct answer is A. Preliminary scope statement. A preliminary scope statement is created during project initiation to capture high-level goals, objectives, milestones, and requirements based on the information available at that time. The word 'preliminary' is the key signal - it is intentionally incomplete and is expected to…
Question
During project initiation, a project manager is drafting a document that includes an outline of the high-level goals, objectives, milestones, and requirements. This document will be modified and finalized as more information becomes available. Which of the following best meets the requirements?
Options
- APreliminary scope statement
- BProcurement needs assessment
- CProject success criteria
- DWork breakdown structure
How the community answered
(57 responses)- A70% (40)
- B9% (5)
- C18% (10)
- D4% (2)
Explanation
A preliminary scope statement is created during project initiation to capture high-level goals, objectives, milestones, and requirements based on the information available at that time. The word 'preliminary' is the key signal - it is intentionally incomplete and is expected to be refined as the project progresses. A procurement needs assessment (B) is specific to vendor and purchasing decisions. Project success criteria (C) define how success will be measured, not the full scope. A work breakdown structure (D) is a detailed decomposition tool created after scope is better defined, not during early initiation.