PK0-005 · Question #429
The client asks the project manager to establish a communication channel. The client wants to understand what is needed from them and to know the project's level of compliance with the budget. Which…
The correct answer is D. Send a weekly status report by email. To keep the client informed about project needs and budget compliance, the project manager should send a weekly status report by email. This report provides a structured and documented update on project progress, budget status, and any actions required from the client. Regular…
Question
The client asks the project manager to establish a communication channel. The client wants to understand what is needed from them and to know the project's level of compliance with the budget. Which of the following best describes what the project manager should do to assist the client?
Options
- AGrant the client access to the project repository.
- BCreate a chat to communicate in real time.
- CSchedule a weekly status meeting.
- DSend a weekly status report by email.
How the community answered
(41 responses)- A5% (2)
- B10% (4)
- C2% (1)
- D83% (34)
Explanation
To keep the client informed about project needs and budget compliance, the project manager should send a weekly status report by email. This report provides a structured and documented update on project progress, budget status, and any actions required from the client. Regular status reporting is a key component of effective communication management. It ensures that stakeholders are kept informed and engaged throughout the project lifecycle.