nerdexam
CompTIACompTIA

PK0-005 · Question #427

PK0-005 Question #427: Real Exam Question with Answer & Explanation

The correct answer is A: Perform a gap analysis.. When a project manager observes that the project's outcomes do not align with expectations, despite the vendor fulfilling all contractual obligations as per the Statement of Work (SOW), the appropriate next step is to perform a gap analysis. This analysis helps identify discrepan

Project Management Concepts

Question

A project manager was concerned the results were not fulfilling the expectations at the end of the execution phase. After reviewing the SOW, the project manager realized the vendor delivered everything included in the contract. Which of the following actions should the project manager complete next?

Options

  • APerform a gap analysis.
  • BEscalate the issue.
  • CSubmit a change request.
  • DApprove deliverables.

Explanation

When a project manager observes that the project's outcomes do not align with expectations, despite the vendor fulfilling all contractual obligations as per the Statement of Work (SOW), the appropriate next step is to perform a gap analysis. This analysis helps identify discrepancies between the current state (what has been delivered) and the desired state (stakeholder

Topics

#Project Scope Management#Expectation Management#Gap Analysis#Contract Management

Community Discussion

No community discussion yet for this question.

Full PK0-005 PracticeBrowse All PK0-005 Questions