PK0-005 · Question #415
PK0-005 Question #415: Real Exam Question with Answer & Explanation
The correct answer is C: Communicate with the project sponsor.. Before making a scope change in the Statement of Work (SOW), the project manager must first communicate with the project sponsor, as they provide authorization and oversight for project changes. The sponsor's approval is often required for significant changes, especially those af
Question
A project manager has decided to make a scope change in the SOW. Which of the following should the project manager do first in the process?
Options
- ADiscuss with a team lead.
- BMove to the next step in the process.
- CCommunicate with the project sponsor.
- DHave a meeting with the human resources department.
Explanation
Before making a scope change in the Statement of Work (SOW), the project manager must first communicate with the project sponsor, as they provide authorization and oversight for project changes. The sponsor's approval is often required for significant changes, especially those affecting scope, budget, or timelines. After obtaining approval, the project manager can then follow the change management process, which may include discussions with team leads and other stakeholders.
Topics