PK0-005 · Question #402
The development phase of a project is coming to an end, and the product is ready. The project manager needs to develop a transition/release plan to ensure a smooth launch. Which of the following…
The correct answer is C. Operational handoff. The operational handoff should be included in the transition/release plan. This involves transferring the product or service from the project team to the operations or support team, ensuring that they have the necessary documentation, training, and resources to manage the…
Question
The development phase of a project is coming to an end, and the product is ready. The project manager needs to develop a transition/release plan to ensure a smooth launch. Which of the following activities should be included in the plan?
Options
- APreliminary needs assessment
- BWork breakdown structure
- COperational handoff
- DBudget reconciliation
How the community answered
(29 responses)- A3% (1)
- B3% (1)
- C93% (27)
Explanation
The operational handoff should be included in the transition/release plan. This involves transferring the product or service from the project team to the operations or support team, ensuring that they have the necessary documentation, training, and resources to manage the product moving forward. It is a critical step to ensure a smooth launch and continued success after the development phase.
Topics