PK0-005 · Question #400
During an active project, the finished product is not meeting quality specifications. Which of the following actions should be taken after the project manager determines what would be needed to…
The correct answer is C. Create a change request. Once the project manager determines what needs to be done to resolve the issues, the next step is to create a change request. A change request formally documents the need for a modification to the project scope, schedule, or resources in order to address the quality issues…
Question
During an active project, the finished product is not meeting quality specifications. Which of the following actions should be taken after the project manager determines what would be needed to resolve the issues?
Options
- ACommunicate the change status.
- BDocument change recommendations.
- CCreate a change request.
- DImplement the changes.
How the community answered
(28 responses)- A4% (1)
- B11% (3)
- C82% (23)
- D4% (1)
Explanation
Once the project manager determines what needs to be done to resolve the issues, the next step is to create a change request. A change request formally documents the need for a modification to the project scope, schedule, or resources in order to address the quality issues. This allows for proper review, approval, and tracking of the changes, ensuring that all stakeholders are aligned before any changes are implemented.
Topics
Community Discussion
No community discussion yet for this question.