nerdexam
CompTIA

PK0-005 · Question #400

During an active project, the finished product is not meeting quality specifications. Which of the following actions should be taken after the project manager determines what would be needed to…

The correct answer is C. Create a change request. Once the project manager determines what needs to be done to resolve the issues, the next step is to create a change request. A change request formally documents the need for a modification to the project scope, schedule, or resources in order to address the quality issues…

Project Management Concepts

Question

During an active project, the finished product is not meeting quality specifications. Which of the following actions should be taken after the project manager determines what would be needed to resolve the issues?

Options

  • ACommunicate the change status.
  • BDocument change recommendations.
  • CCreate a change request.
  • DImplement the changes.

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    11% (3)
  • C
    82% (23)
  • D
    4% (1)

Explanation

Once the project manager determines what needs to be done to resolve the issues, the next step is to create a change request. A change request formally documents the need for a modification to the project scope, schedule, or resources in order to address the quality issues. This allows for proper review, approval, and tracking of the changes, ensuring that all stakeholders are aligned before any changes are implemented.

Topics

#Change Management#Quality Management#Project Control#Corrective Action

Community Discussion

No community discussion yet for this question.

Full PK0-005 Practice