PK0-005 · Question #395
Which of the following best explains the importance of artifacts during the discovery/concept preparation phase of a project?
The correct answer is D. To ensure that all stakeholders have a shared understanding of the project's objectives. During the discovery/concept preparation phase, artifacts (such as documents, diagrams, and prototypes) are created to ensure that all stakeholders have a clear and shared understanding of the project's objectives, scope, and goals. These artifacts serve as a foundation for…
Question
Which of the following best explains the importance of artifacts during the discovery/concept preparation phase of a project?
Options
- ATo develop a detailed project plan and timeline
- BTo enable a lessons learned session
- CTo identify and assess potential vendors for the project
- DTo ensure that all stakeholders have a shared understanding of the project's objectives
How the community answered
(38 responses)- B3% (1)
- C3% (1)
- D95% (36)
Explanation
During the discovery/concept preparation phase, artifacts (such as documents, diagrams, and prototypes) are created to ensure that all stakeholders have a clear and shared understanding of the project's objectives, scope, and goals. These artifacts serve as a foundation for aligning the team and stakeholders before moving forward with detailed planning and execution.
Topics
Community Discussion
No community discussion yet for this question.