PK0-005 · Question #388

A sponsor is working on a document that states the objectives and success criteria of the project, as well as the person to be appointed as project manager. Which of the following should the newly…

The correct answer is C. Identify stakeholders. The newly appointed project manager should identify stakeholders next. Understanding who the stakeholders are, their interests, and their influence on the project is crucial for planning and managing the project effectively. Stakeholder identification allows the project manager…

Project Life Cycle Phases

Question

A sponsor is working on a document that states the objectives and success criteria of the project, as well as the person to be appointed as project manager. Which of the following should the newly appointed project manager do next?

Options

  • AConduct a risk assessment.
  • BCreate a project scope document.
  • CIdentify stakeholders.
  • DPerform a lessons learned.

How the community answered

(29 responses)
  • A
    3% (1)
  • B
    7% (2)
  • C
    76% (22)
  • D
    14% (4)

Explanation

The newly appointed project manager should identify stakeholders next. Understanding who the stakeholders are, their interests, and their influence on the project is crucial for planning and managing the project effectively. Stakeholder identification allows the project manager to tailor communication and ensure that the right people are engaged throughout the project lifecycle.

Topics

#Project initiation#Stakeholder identification#Project manager responsibilities#Project life cycle