PK0-005 · Question #382
Several stakeholders have asked about how the requirements are being covered by the deliverables and the progress of each requirement. Which of the following would be the best tool the project…
The correct answer is C. Traceability matrix. A Requirements Traceability Matrix (RTM) (C) is a document that maps and traces each requirement to its corresponding project deliverable, test case, and current status. It directly answers the stakeholders' question by showing which requirements are covered, by what…
Question
Several stakeholders have asked about how the requirements are being covered by the deliverables and the progress of each requirement. Which of the following would be the best tool the project manager can use to provide this information to the stakeholders?
Options
- ARisk register
- BChange log
- CTraceability matrix
- DProject status report
How the community answered
(26 responses)- A4% (1)
- B15% (4)
- C73% (19)
- D8% (2)
Explanation
A Requirements Traceability Matrix (RTM) (C) is a document that maps and traces each requirement to its corresponding project deliverable, test case, and current status. It directly answers the stakeholders' question by showing which requirements are covered, by what deliverable, and the completion/progress status of each. A risk register (A) tracks identified risks and responses. A change log (B) records approved changes to the project. A project status report (D) provides a general overview of schedule, cost, and scope - but does not provide the requirement-to-deliverable mapping the stakeholders need.
Topics
Community Discussion
No community discussion yet for this question.