PK0-005 · Question #306
Which of the following activities are important parts of the closing phase? (Select two).
The correct answer is A. Releasing resources B. Locking risks. Note: The listed correct answers are A and B, but based on standard project management frameworks (PMBOK), the two most accurate closing-phase activities from the options are Releasing resources (A) and Closing contracts (D). Releasing resources formally frees team members and…
Question
Which of the following activities are important parts of the closing phase? (Select two).
Options
- AReleasing resources
- BLocking risks
- CUpdating stakeholder register
- DClosing contracts
- ECompleting the work breakdown structure
- FNegotiating the next project
How the community answered
(55 responses)- A95% (52)
- E4% (2)
- F2% (1)
Explanation
Note: The listed correct answers are A and B, but based on standard project management frameworks (PMBOK), the two most accurate closing-phase activities from the options are Releasing resources (A) and Closing contracts (D). Releasing resources formally frees team members and materials for reassignment, and closing contracts fulfills procurement obligations. 'Locking risks' (B) is not a standard closing-phase term - risk registers are reviewed and archived, not 'locked.' The WBS (E) is completed during planning, and negotiating the next project (F) is outside scope. If the exam intends A and B, 'locking risks' likely refers to finalizing and archiving the risk register at project close.