PK0-005 · Question #301
Which of the following PRINCE2 processes includes creating the project plan?
The correct answer is B. Initiating a project. In PRINCE2, the 'Initiating a Project' process is where the detailed Project Initiation Documentation (PID) is assembled, which includes the project plan (covering schedule, budget, and resource allocation). 'Starting Up a Project' is a pre-initiation process that produces only…
Question
Which of the following PRINCE2 processes includes creating the project plan?
Options
- AStarting up a project
- BInitiating a project
- CManaging product delivery
- DDirecting a project
How the community answered
(27 responses)- B96% (26)
- D4% (1)
Explanation
In PRINCE2, the 'Initiating a Project' process is where the detailed Project Initiation Documentation (PID) is assembled, which includes the project plan (covering schedule, budget, and resource allocation). 'Starting Up a Project' is a pre-initiation process that produces only a project brief and outline business case. 'Managing Product Delivery' focuses on executing and delivering work packages. 'Directing a Project' is the Project Board's oversight process for authorization decisions - not planning. The project plan is formally created during initiation.