PK0-005 · Question #301

PK0-005 Question #301: Real Exam Question with Answer & Explanation

The correct answer is B: Initiating a project. {"question_number": 7, "explanation": "In PRINCE2, the 'Initiating a Project' process is where the detailed Project Initiation Documentation (PID) is assembled, which includes the project plan (covering schedule, budget, and resource allocation). 'Starting Up a Project' is a pre-

Project Life Cycle Phases

Question

Which of the following PRINCE2 processes includes creating the project plan?

Options

  • AStarting up a project
  • BInitiating a project
  • CManaging product delivery
  • DDirecting a project

Explanation

{"question_number": 7, "explanation": "In PRINCE2, the 'Initiating a Project' process is where the detailed Project Initiation Documentation (PID) is assembled, which includes the project plan (covering schedule, budget, and resource allocation). 'Starting Up a Project' is a pre-initiation process that produces only a project brief and outline business case. 'Managing Product Delivery' focuses on executing and delivering work packages. 'Directing a Project' is the Project Board's oversight process for authorization decisions - not planning. The project plan is formally created during initiation.", "generated_by": "claude-sonnet", "llm_judge_score": 5}

Topics

#PRINCE2#Project Planning#Project Initiation#Project Management Process