nerdexam
CompTIA

PK0-005 · Question #290

Before a configuration can be made to a system in development, a document containing information about how the new system will interact with other systems within the organization needs to be…

The correct answer is D. Finish-to-start. Finish-to-start (FS) is the most common task dependency: the predecessor task must finish before the successor task can start. Here, writing the document (predecessor) must be completed (finish) before the system configuration (successor) can begin (start) - a classic FS…

Project Management Concepts

Question

Before a configuration can be made to a system in development, a document containing information about how the new system will interact with other systems within the organization needs to be written. Which of the following relationships best describes this scenario?

Options

  • AStart-to-start
  • BStart-to-finish
  • CFinish-to-finish
  • DFinish-to-start

How the community answered

(63 responses)
  • A
    2% (1)
  • B
    3% (2)
  • C
    8% (5)
  • D
    87% (55)

Explanation

Finish-to-start (FS) is the most common task dependency: the predecessor task must finish before the successor task can start. Here, writing the document (predecessor) must be completed (finish) before the system configuration (successor) can begin (start) - a classic FS relationship. Start-to-start (A) means both tasks begin at the same time. Start-to-finish (B) means the successor cannot finish until the predecessor starts - a rarely used relationship. Finish-to-finish (C) means both tasks must end at the same time. Only finish-to-start correctly captures 'document must be written before configuration begins.'

Topics

#Project dependencies#Task relationships#Activity sequencing#Finish-to-start

Community Discussion

No community discussion yet for this question.

Full PK0-005 Practice