nerdexam
CompTIACompTIA

PK0-005 · Question #290

PK0-005 Question #290: Real Exam Question with Answer & Explanation

The correct answer is D: Finish-to-start. A finish-to-start relationship is a type of logical dependency between two tasks, in which the first task must be completed before the second task can start. In this scenario, the document containing information about how the new system will interact with other systems within the

Project Management Concepts

Question

Before a configuration can be made to a system in development, a document containing information about how the new system will interact with other systems within the organization needs to be written. Which of the following relationships best describes this scenario?

Options

  • AStart-to-start
  • BStart-to-finish
  • CFinish-to-finish
  • DFinish-to-start

Explanation

A finish-to-start relationship is a type of logical dependency between two tasks, in which the first task must be completed before the second task can start. In this scenario, the document containing information about how the new system will interact with other systems within the organization is a prerequisite for the configuration of the system in development. Therefore, the document writing task must finish before the configuration task can start, which is a finish-to-start

Topics

#Project dependencies#Task relationships#Activity sequencing#Finish-to-start

Community Discussion

No community discussion yet for this question.

Full PK0-005 PracticeBrowse All PK0-005 Questions