PK0-005 · Question #286
A project team participates in a brainstorming session to define the guidance, direction, and approach for monitoring established procedures for developed products. Which of the following plans is…
The correct answer is D. Project quality assurance. The team is creating a Project quality assurance plan. This plan defines the guidance, direction, and approach for monitoring the established procedures and ensuring that developed products meet the required quality standards. Quality assurance involves setting up processes and…
Question
A project team participates in a brainstorming session to define the guidance, direction, and approach for monitoring established procedures for developed products. Which of the following plans is the team creating?
Options
- AProject transition
- BProject management
- CProject communications
- DProject quality assurance
How the community answered
(46 responses)- A7% (3)
- B13% (6)
- C4% (2)
- D76% (35)
Explanation
The team is creating a Project quality assurance plan. This plan defines the guidance, direction, and approach for monitoring the established procedures and ensuring that developed products meet the required quality standards. Quality assurance involves setting up processes and procedures to monitor and improve the quality of the deliverables throughout the project lifecycle.