PK0-005 · Question #277

Two stakeholders, who have a history of animosity toward one another, are in disagreement during a project. The project's timeline depends on the stakeholders accomplishing their tasks. Which of the…

The correct answer is B. Confronting. Confronting, also known as problem-solving or collaborating, is a method of conflict resolution that involves addressing the root cause of the conflict and finding a mutually beneficial solution that satisfies both parties. Confronting is the most effective method when the…

Project Management Concepts

Question

Two stakeholders, who have a history of animosity toward one another, are in disagreement during a project. The project's timeline depends on the stakeholders accomplishing their tasks. Which of the following conflict resolution methods would be best to utilize?

Options

  • ASmoothing
  • BConfronting
  • CForcing
  • DCompromising

How the community answered

(20 responses)
  • A
    5% (1)
  • B
    75% (15)
  • C
    5% (1)
  • D
    15% (3)

Explanation

Confronting, also known as problem-solving or collaborating, is a method of conflict resolution that involves addressing the root cause of the conflict and finding a mutually beneficial solution that satisfies both parties. Confronting is the most effective method when the stakes are high and the relationship is important, as it can lead to increased trust, respect, and cooperation. Confronting requires open communication, active listening, empathy, and creativity from both parties. Confronting is the best method to use in this scenario, as it can help the stakeholders overcome their personal animosity, focus on their common goals, and work together to complete their tasks on time.

Topics

#Conflict resolution#Stakeholder management#Project management#Communication skills

Community Discussion

No community discussion yet for this question.