nerdexam
CompTIACompTIA

PK0-005 · Question #192

PK0-005 Question #192: Real Exam Question with Answer & Explanation

Sign in or unlock PK0-005 to reveal the answer and full explanation for question #192. The question stem and answer options stay visible for context.

Project Management Concepts

Question

A project manager is overseeing the implementation of a major upgrade to a critical ERP system. The project sponsor is requiring that the upgrade should not exceed more than three hours of downtime for the implementation and validation in production. During cutover, the team runs into a validation issue after 2.5 hours, and the process is only 70% through the validation steps Which of the following actions should the project manager take?

Options

  • ANotify customers the downtime will take longer than expected.
  • BAdd new team members to help speed up validation.
  • CBegin executing the rollback plan.
  • DRecord the issue and proceed with the implementation.

Unlock PK0-005 to see the answer

You've previewed enough free PK0-005 questions. Unlock PK0-005 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Cutover management#Rollback planning#Downtime constraints#Risk response
Full PK0-005 PracticeBrowse All PK0-005 Questions