PK0-005 · Question #190

A project manager has decided to wait until all requirements are developed to initiate testing. Which of the following relationship dependencies is the project manager using?

The correct answer is C. Finish-to-start. A finish-to-start dependency is a type of relationship dependency in project management, where the start of one task depends on the finish of another task. In this case, the project manager is using a finish-to-start dependency, because testing cannot start until requirements…

Project Management Concepts

Question

A project manager has decided to wait until all requirements are developed to initiate testing. Which of the following relationship dependencies is the project manager using?

Options

  • AStart-to-finish
  • BFinish-to-finish
  • CFinish-to-start
  • DStart-to-start

How the community answered

(55 responses)
  • A
    5% (3)
  • B
    2% (1)
  • C
    91% (50)
  • D
    2% (1)

Explanation

A finish-to-start dependency is a type of relationship dependency in project management, where the start of one task depends on the finish of another task. In this case, the project manager is using a finish-to-start dependency, because testing cannot start until requirements development This implies that testing is a successor task, and requirements development is a predecessor task. A finish-to-start dependency is the most common type of dependency in project management, and it ensures that tasks are performed in a logical sequence.

Topics

#Activity dependencies#Finish-to-start#Project scheduling#Task sequencing