PK0-005 · Question #190

PK0-005 Question #190: Real Exam Question with Answer & Explanation

The correct answer is C: Finish-to-start. A finish-to-start dependency is a type of relationship dependency in project management, where the start of one task depends on the finish of another task. In this case, the project manager is using a finish-to-start dependency, because testing cannot start until requirements dev

Project Management Concepts

Question

A project manager has decided to wait until all requirements are developed to initiate testing. Which of the following relationship dependencies is the project manager using?

Options

  • AStart-to-finish
  • BFinish-to-finish
  • CFinish-to-start
  • DStart-to-start

Explanation

A finish-to-start dependency is a type of relationship dependency in project management, where the start of one task depends on the finish of another task. In this case, the project manager is using a finish-to-start dependency, because testing cannot start until requirements development This implies that testing is a successor task, and requirements development is a predecessor task. A finish-to-start dependency is the most common type of dependency in project management, and it ensures that tasks are performed in a logical sequence.

Topics

#Activity dependencies#Finish-to-start#Project scheduling#Task sequencing