PK0-005 · Question #184
Although a project was successfully released into production a month ago, a project manager continues to receive project-related work. Which of the following is the reason for this issue?
The correct answer is C. The project manager did not complete the project closure phase. If a project manager continues to receive project-related work after the project has been released into production, it suggests that the project closure phase was not completed properly. The project closure phase involves several activities, including ensuring that all project…
Question
Although a project was successfully released into production a month ago, a project manager continues to receive project-related work. Which of the following is the reason for this issue?
Options
- AThe project manager did not release the resources.
- BThe project is in the verification testing phase.
- CThe project manager did not complete the project closure phase.
- DThe project manager did not remove access.
How the community answered
(24 responses)- A4% (1)
- C96% (23)
Explanation
If a project manager continues to receive project-related work after the project has been released into production, it suggests that the project closure phase was not completed properly. The project closure phase involves several activities, including ensuring that all project deliverables are accepted, documenting the lessons learned, releasing project resources, and formally closing the project. If these activities are not completed, the project can remain `open' in a sense, leading to continued work and inquiries.
Topics
Community Discussion
No community discussion yet for this question.