PK0-005 · Question #181
Given the following network diagram: Which of the following is the critical path?
The correct answer is A. A-C-G-K-M. The critical path is the sequence of tasks that determines the minimum project duration. It is the longest path through the network diagram and has the least amount of slack or float. Based on the provided network diagram, the critical path is A-C-G-K-M, which has the longest…
Question
Given the following network diagram:
Which of the following is the critical path?
Exhibit
Options
- AA-C-G-K-M
- BA-B-D-l-L-M
- CA-B-E-J-L-M
- DA-B-F-L-M
How the community answered
(33 responses)- A76% (25)
- B15% (5)
- C6% (2)
- D3% (1)
Explanation
The critical path is the sequence of tasks that determines the minimum project duration. It is the longest path through the network diagram and has the least amount of slack or float. Based on the provided network diagram, the critical path is A-C-G-K-M, which has the longest total duration when adding up the individual task durations.