nerdexam
CompTIA

PK0-005 · Question #181

Given the following network diagram: Which of the following is the critical path?

The correct answer is A. A-C-G-K-M. The critical path is the sequence of tasks that determines the minimum project duration. It is the longest path through the network diagram and has the least amount of slack or float. Based on the provided network diagram, the critical path is A-C-G-K-M, which has the longest…

Project Management Concepts

Question

Given the following network diagram:

Which of the following is the critical path?

Exhibit

PK0-005 question #181 exhibit

Options

  • AA-C-G-K-M
  • BA-B-D-l-L-M
  • CA-B-E-J-L-M
  • DA-B-F-L-M

How the community answered

(33 responses)
  • A
    76% (25)
  • B
    15% (5)
  • C
    6% (2)
  • D
    3% (1)

Explanation

The critical path is the sequence of tasks that determines the minimum project duration. It is the longest path through the network diagram and has the least amount of slack or float. Based on the provided network diagram, the critical path is A-C-G-K-M, which has the longest total duration when adding up the individual task durations.

Topics

#Critical Path Method#Project scheduling#Network diagrams#Activity sequencing

Community Discussion

No community discussion yet for this question.

Full PK0-005 Practice