PK0-005 · Question #176
A project is running over budget, and due to new legislation in the country, the company needs to release all its contractors on the project or hire them as full-time employees. Which of the…
The correct answer is A. Use only full-time employees even if the project is delayed. In response to new legislation requiring the release of contractors or their conversion to full-time employees, the project manager should prioritize compliance with the law. This may involve using only full-time employees, even if it results in project delays. The focus should…
Question
A project is running over budget, and due to new legislation in the country, the company needs to release all its contractors on the project or hire them as full-time employees. Which of the following should the PM do next to comply with the new legislation?
Options
- AUse only full-time employees even if the project is delayed.
- BHire all team members to avoid any delay in the project.
- CClose the contract and pay the contractors cash for the remainder of the project.
- DLook for an overseas vendor to finalize the project work.
How the community answered
(19 responses)- A79% (15)
- B5% (1)
- C5% (1)
- D11% (2)
Explanation
In response to new legislation requiring the release of contractors or their conversion to full-time employees, the project manager should prioritize compliance with the law. This may involve using only full-time employees, even if it results in project delays. The focus should be on legal compliance and the ethical treatment of workers, rather than solely on project timelines.