PK0-005 · Question #140

PK0-005 Question #140: Real Exam Question with Answer & Explanation

The correct answer is A: PM. The project manager is typically responsible for managing and approving minor changes and updates to project documentation like the project management plan.

Project Management Concepts

Question

A stakeholder notices a typo in the project management plan, specifically the word manager was spelled 搈anger? Which of the following is the decision maker who can authorize the change so the correction can be made?

Options

  • APM
  • BCCB
  • CSponsor
  • DBusiness analyst

Explanation

The project manager is typically responsible for managing and approving minor changes and updates to project documentation like the project management plan.

Common mistakes.

  • B. The Change Control Board (CCB) is usually convened for significant changes that impact scope, budget, schedule, or quality, not minor typographical corrections.
  • C. The Project Sponsor provides overall project funding and high-level direction, but typically delegates day-to-day document maintenance and minor corrections to the Project Manager.
  • D. A Business Analyst primarily focuses on requirements gathering and analysis, not the authorization of changes to project management plans.

Concept tested. Project manager authority for minor changes

Topics

#Project Manager authority#Change control#Project documentation#Roles and responsibilities