nerdexam
CompTIA

PK0-005 · Question #134

Two projects share resources. The mobile application project cannot start if the database renewal project has not started. Which of the following relationships describes this situation?

The correct answer is B. Start-to-start. This scenario describes a relationship where the start of one activity is dependent on the start of another activity.

Project Management Concepts

Question

Two projects share resources. The mobile application project cannot start if the database renewal project has not started. Which of the following relationships describes this situation?

Options

  • AStart-to-finish
  • BStart-to-start
  • CFinish-to-start
  • DFinish-to-finish

How the community answered

(53 responses)
  • A
    2% (1)
  • B
    94% (50)
  • D
    4% (2)

Why each option

This scenario describes a relationship where the start of one activity is dependent on the start of another activity.

AStart-to-finish

A Start-to-Finish (SF) relationship means the successor activity cannot finish until the predecessor activity has started.

BStart-to-startCorrect

A Start-to-Start (SS) relationship means that the successor activity cannot start until the predecessor activity has started. In this case, the mobile application project (successor) cannot start until the database renewal project (predecessor) has started.

CFinish-to-start

A Finish-to-Start (FS) relationship means the successor activity cannot start until the predecessor activity has finished.

DFinish-to-finish

A Finish-to-Finish (FF) relationship means the successor activity cannot finish until the predecessor activity has finished.

Concept tested: Project schedule activity dependencies

Topics

#Project scheduling#Dependency types#Start-to-start relationship

Community Discussion

No community discussion yet for this question.

Full PK0-005 Practice