PK0-005 · Question #111
Which of the following key project elements is used to organize deliverables into manageable pieces to ensure the proper steps are executed and to achieve the project's core objectives?
The correct answer is A. WBS. The Work Breakdown Structure (WBS) is a key project element used to organize deliverables into smaller, manageable pieces to ensure all proper steps are executed.
Question
Which of the following key project elements is used to organize deliverables into manageable pieces to ensure the proper steps are executed and to achieve the project's core objectives?
Options
- AWBS
- BRACI
- CRFP
- DPERT
How the community answered
(59 responses)- A90% (53)
- B2% (1)
- C3% (2)
- D5% (3)
Why each option
The Work Breakdown Structure (WBS) is a key project element used to organize deliverables into smaller, manageable pieces to ensure all proper steps are executed.
A Work Breakdown Structure (WBS) is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables. It breaks down the project into manageable sections, making it easier to plan, estimate, and control the project work.
RACI is a responsibility assignment matrix (Responsible, Accountable, Consulted, Informed) used to clarify roles and responsibilities, not to organize deliverables into manageable pieces.
An RFP (Request for Proposal) is a document used in procurement to solicit bids from potential vendors, not an element for organizing project deliverables internally.
PERT (Program Evaluation and Review Technique) is a project management tool used for scheduling, organizing, and coordinating tasks within a project, often visualized as a network diagram, but it is not the primary element for breaking down deliverables themselves.
Concept tested: Work Breakdown Structure (WBS)
Topics
Community Discussion
No community discussion yet for this question.