PK0-005 · Question #106
A meeting agenda included the following items: - Review the goals of the project. - Review the progress of the project. - Discuss if the project is ready to move forward. Which of the following BEST…
The correct answer is D. Gate review. A meeting that reviews project goals, progress, and readiness to proceed to the next stage is best described as a gate review, a formal checkpoint in the project lifecycle.
Question
A meeting agenda included the following items:
- Review the goals of the project.
- Review the progress of the project.
- Discuss if the project is ready to move forward.
Which of the following BEST describes this type of meeting?
Options
- AStand-up
- BMonthly status
- CGap analysis
- DGate review
How the community answered
(36 responses)- A3% (1)
- B3% (1)
- C6% (2)
- D89% (32)
Why each option
A meeting that reviews project goals, progress, and readiness to proceed to the next stage is best described as a gate review, a formal checkpoint in the project lifecycle.
A stand-up meeting is a short daily meeting focused on recent progress, immediate plans, and impediments, not a comprehensive review of project goals and readiness to move forward to a new phase.
A monthly status meeting provides an update on progress but typically lacks the formal decision-making authority and comprehensive evaluation required to determine project readiness to advance.
A gap analysis focuses on identifying the difference between the current state and a desired future state, which is a specific analytical activity, not a general project progress and readiness review meeting.
A gate review, also known as a phase-gate review, is a formal checkpoint at the end of a project phase to evaluate progress against goals, assess readiness, and decide whether to proceed to the next phase. This type of meeting ensures that the project is on track and viable for future investment.
Concept tested: Project lifecycle gate review
Topics
Community Discussion
No community discussion yet for this question.