nerdexam
CompTIACompTIA

PK0-005 · Question #102

PK0-005 Question #102: Real Exam Question with Answer & Explanation

Sign in or unlock PK0-005 to reveal the answer and full explanation for question #102. The question stem and answer options stay visible for context.

Project Management Concepts

Question

A PM is evaluating whether an IaaS contract needs to be extended. When reviewing the system usage report, the PM realizes that usage is at 20% capacity. Which of the following actions should the PM take?

Options

  • AContinue to monitor the system performance.
  • BResize the resource utilization to reflect current needs.
  • CReinforce adoption over time.
  • DRaise an item in the issue log.

Unlock PK0-005 to see the answer

You've previewed enough free PK0-005 questions. Unlock PK0-005 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Resource Management#Cloud Services#Cost Optimization#Project Control
Full PK0-005 PracticeBrowse All PK0-005 Questions