Project Management Concepts
Question
A PM is evaluating whether an IaaS contract needs to be extended. When reviewing the system usage report, the PM realizes that usage is at 20% capacity. Which of the following actions should the PM take?
Options
- AContinue to monitor the system performance.
- BResize the resource utilization to reflect current needs.
- CReinforce adoption over time.
- DRaise an item in the issue log.