nerdexam
CompTIA

PK0-004 · Question #959

A company is conducting a project that is expected to have positive effects on a local town. The townspeople are excited about the project and want to help make it a success, but they are nervous…

The correct answer is A. Issue a regularly scheduled social media message highlighting the benefits to the town. The townspeople are external stakeholders who are anxious due to a lack of updates - a classic stakeholder communication gap. The project manager's job is to define and execute a stakeholder communication plan. Issuing regularly scheduled social media messages (A) directly…

Project management concepts

Question

A company is conducting a project that is expected to have positive effects on a local town. The townspeople are excited about the project and want to help make it a success, but they are nervous because updates have not been released for a while. Which of the following explains how the project manager can ensure the project is a success?

Options

  • AIssue a regularly scheduled social media message highlighting the benefits to the town.
  • BAdd key townspeople to the project team to ensure they are involved.
  • CProvide the town's government officials with regular verbal updates.
  • DAdd townspeople gate reviews to the project schedule.

How the community answered

(44 responses)
  • A
    73% (32)
  • B
    5% (2)
  • C
    16% (7)
  • D
    7% (3)

Explanation

The townspeople are external stakeholders who are anxious due to a lack of updates - a classic stakeholder communication gap. The project manager's job is to define and execute a stakeholder communication plan. Issuing regularly scheduled social media messages (A) directly addresses the root cause: absence of consistent, accessible updates for the public. It creates a predictable cadence that manages expectations and maintains stakeholder confidence. Option B (adding townspeople to the team) oversteps appropriate boundaries and introduces unnecessary complexity. Option C (verbal updates to government officials only) excludes the broader public and relies on officials to relay information, which is unreliable. Option D (gate reviews with townspeople) would slow the project and is not a standard stakeholder engagement mechanism for the general public. Regular, public-facing communication is the PMI-aligned response for managing community stakeholders.

Topics

#stakeholder management#communication plan#external stakeholders#social media

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice