PK0-004 · Question #959
A company is conducting a project that is expected to have positive effects on a local town. The townspeople are excited about the project and want to help make it a success, but they are nervous…
The correct answer is A. Issue a regularly scheduled social media message highlighting the benefits to the town. The townspeople are external stakeholders who are anxious due to a lack of updates - a classic stakeholder communication gap. The project manager's job is to define and execute a stakeholder communication plan. Issuing regularly scheduled social media messages (A) directly…
Question
A company is conducting a project that is expected to have positive effects on a local town. The townspeople are excited about the project and want to help make it a success, but they are nervous because updates have not been released for a while. Which of the following explains how the project manager can ensure the project is a success?
Options
- AIssue a regularly scheduled social media message highlighting the benefits to the town.
- BAdd key townspeople to the project team to ensure they are involved.
- CProvide the town's government officials with regular verbal updates.
- DAdd townspeople gate reviews to the project schedule.
How the community answered
(44 responses)- A73% (32)
- B5% (2)
- C16% (7)
- D7% (3)
Explanation
The townspeople are external stakeholders who are anxious due to a lack of updates - a classic stakeholder communication gap. The project manager's job is to define and execute a stakeholder communication plan. Issuing regularly scheduled social media messages (A) directly addresses the root cause: absence of consistent, accessible updates for the public. It creates a predictable cadence that manages expectations and maintains stakeholder confidence. Option B (adding townspeople to the team) oversteps appropriate boundaries and introduces unnecessary complexity. Option C (verbal updates to government officials only) excludes the broader public and relies on officials to relay information, which is unreliable. Option D (gate reviews with townspeople) would slow the project and is not a standard stakeholder engagement mechanism for the general public. Regular, public-facing communication is the PMI-aligned response for managing community stakeholders.