PK0-004 · Question #959
PK0-004 Question #959: Real Exam Question with Answer & Explanation
Sign in or unlock PK0-004 to reveal the answer and full explanation for question #959. The question stem and answer options stay visible for context.
Question
A company is conducting a project that is expected to have positive effects on a local town. The townspeople are excited about the project and want to help make it a success, but they are nervous because updates have not been released for a while. Which of the following explains how the project manager can ensure the project is a success?
Options
- AIssue a regularly scheduled social media message highlighting the benefits to the town.
- BAdd key townspeople to the project team to ensure they are involved.
- CProvide the town's government officials with regular verbal updates.
- DAdd townspeople gate reviews to the project schedule.
Unlock PK0-004 to see the answer