CompTIA
PK0-004 · Question #939
A change request has been submitted to change the construction material from cinder block to wood frame. Which of the following should be performed FIRST after the change has been approved by the…
The correct answer is B. Quality check. Quality check before document.
Project management concepts
Question
A change request has been submitted to change the construction material from cinder block to wood frame. Which of the following should be performed FIRST after the change has been approved by the sponsor?
Options
- ADocumentation update and review
- BQuality check
- CTeam approval
- DImpact analysis
How the community answered
(40 responses)- A3% (1)
- B80% (32)
- C10% (4)
- D8% (3)
Explanation
Quality check before document.
Topics
#change management#change implementation#quality check#change control process
Community Discussion
No community discussion yet for this question.