PK0-004 · Question #910

During project execution, the IT project manager is informed that some team members currently working on the project will be laid off due to a reorganization of the company. However, deadlines will…

The correct answer is C. the budget and timeline. Losing team members to layoffs while keeping the same deadlines creates pressure on both budget (overtime or contract replacements) and timeline (risk of missing deadlines with reduced capacity).

Project management concepts

Question

During project execution, the IT project manager is informed that some team members currently working on the project will be laid off due to a reorganization of the company. However, deadlines will not change. This will MOST likely impact

Options

  • Athe cost and deliverables.
  • Bthe gate reviews and environment.
  • Cthe budget and timeline.
  • Dthe stakeholders and risks.

How the community answered

(28 responses)
  • A
    14% (4)
  • B
    4% (1)
  • C
    75% (21)
  • D
    7% (2)

Why each option

Losing team members to layoffs while keeping the same deadlines creates pressure on both budget (overtime or contract replacements) and timeline (risk of missing deadlines with reduced capacity).

Athe cost and deliverables.

Deliverables define what the project produces and are not directly altered by a staffing reduction - the same outputs are still expected.

Bthe gate reviews and environment.

Gate reviews are predetermined schedule checkpoints and the project environment is not meaningfully affected by internal staff layoffs.

Cthe budget and timeline.Correct

Reduced headcount with unchanged deadlines forces the remaining team to absorb additional work, which typically requires overtime pay or hiring contractors - both of which increase budget. Simultaneously, the reduced capacity introduces risk to the timeline, as fewer resources must deliver the same scope within the original schedule.

Dthe stakeholders and risks.

While stakeholders may be informed and risks updated, these are secondary effects - the direct and primary impact is on budget and the ability to meet the timeline.

Concept tested: Impact of resource loss on project budget and timeline

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#resource reduction#budget impact#organizational change#schedule constraints